Do I Need Planning Permission for a Rear Extension in London? (2026)
When a London rear extension is permitted development, when Prior Approval applies, and when you need full planning permission — depth limits, height and Article 4, explained.
A rear extension is the most common way London homeowners add an open-plan kitchen-diner, and for many houses it can be built under permitted development without a full planning application. But the depth, height and coverage limits are precise, the popular 6m 'larger home' extension follows its own Prior Approval process, and inner-London restrictions remove the rights on many streets. This guide explains exactly when a London rear extension is permitted development, when Prior Approval applies, and when you need full planning permission, in 2026.
As always, the rules are national but their application is local. The permitted-development rights that matter here sit in Schedule 2, Part 1, Class A of the General Permitted Development Order, and their reach on your street depends on your house type, your conservation designation and whether any Article 4 direction is in force. It is also worth understanding that permitted development and full planning are only the two ends of a spectrum: between them sits the Prior Approval process for larger extensions, and running alongside both is building control, which is a separate approval that no planning route removes. Homeowners routinely conflate these, assume that avoiding a planning application means avoiding paperwork, and are surprised when building control asks for structural and drainage detail. We confirm your property's depth allowance, conservation status and any Article 4 direction before drawings are commissioned, free.
When is a rear extension permitted development?
A single-storey rear extension is permitted development when it stays within the standard depth limit for your house type and meets the other conditions — height no more than 4m, eaves no higher than 3m within 2m of a boundary, materials similar to the existing house, and no more than half the garden covered by buildings. The depth is always measured from the original rear wall of the house as it stood in 1948 or as first built, not from a wall added by a previous owner, which is a distinction that catches many homeowners out. Exceed any one condition and the whole extension needs an application — the conditions are cumulative, not a menu.
- 3m depth from the original rear wall for terraced and semi-detached houses
- 4m depth for detached houses
- Maximum height 4m; eaves within 2m of a boundary capped at 3m
- No more than 50% of the original garden/curtilage covered by buildings
- Similar materials to the existing house
- Not forward of the principal elevation onto a highway
What is the 6m 'larger home' extension and Prior Approval?
The Larger Home Extension scheme lets you go deeper — up to 6m for a terraced or semi-detached house and 8m for a detached house — without a full planning application, through a lighter Prior Approval process. You notify the council with a plan showing the depth and the neighbouring properties, and the council writes to the adjoining owners on both sides; if none objects within the 21-day consultation period, or the council rules the impact acceptable, you can build. It is faster and more certain than full planning, but it is not automatic — a neighbour objection brings the council's judgement on amenity into play, and the extension must still respect the 4m height cap and the 50% coverage rule. The right was made permanent in 2019 after years as a temporary measure, so it remains available in 2026. One practical point catches people out: you must not begin work until the council has either confirmed Prior Approval is not required or granted it, and building without waiting can invalidate the right entirely. The Prior Approval fee is lower than a full householder application, and because the council is only assessing the impact on the amenity of neighbouring properties — not the principle or the design — the decision is narrower and usually quicker, provided the notification plan clearly shows the depth, the height and the position of every adjoining property.
When does a rear extension need full planning permission?
Full planning permission is needed once the design or the location steps outside permitted development. A double-storey rear extension, a wraparound that includes a side return, anything over the depth and height limits, and any extension in a conservation area or on an Article 4 street all require a householder planning application. Flats and maisonettes have no extension PD rights at all and always need a full application, usually alongside freeholder consent. A householder application is decided against the council's local plan and design guidance, is publicised to neighbours, and takes a target eight weeks — longer if it goes to committee or attracts objections.
- Two-storey and wraparound rear extensions
- Anything exceeding the depth, height or coverage limits
- Conservation areas and Article 4 direction streets
- Flats and maisonettes — no PD rights
How is the 45-degree neighbour rule assessed?
Even a permitted-development extension is designed with neighbour daylight in mind, and for full applications the council applies a 45-degree test: a line drawn at 45 degrees in plan from the centre of a neighbour's nearest ground-floor window should not be crossed by your extension. Some boroughs also apply a 45-degree test in section, and the BRE daylight and sunlight guidance sits behind more detailed assessments. Extensions that breach these tests are the most common cause of objections and refusals. We design to the rule from the start and check the rear building line so the scheme the council sees is one it can approve.
How much does a rear extension add, and what will it cost to get consent?
Beyond the planning question, homeowners want to know whether the project is worth it and what the paperwork side costs. A well-designed single-storey rear extension typically adds both floor area and value to a London terrace, particularly when it delivers the open-plan kitchen-diner that buyers now expect, though the uplift depends heavily on the borough, the quality of the finish and how much garden you sacrifice.
What are the application fees and drawing costs?
The statutory householder planning application fee is set nationally and paid to the council; a Lawful Development Certificate for a proposed development is charged at half that householder fee. On top of the council fee you need measured survey drawings, existing and proposed plans and elevations, and — for a build — a full set of building-regulations drawings. Our fixed drafting fees are quoted up front with no hidden extras, and because we are a chartered architectural-technologist practice rather than an architect, the fee is typically around 30% lower for the same council-accepted drawings. The drawings a rear extension needs are the same whether the route is permitted development, Prior Approval or full planning: an accurate measured survey, existing and proposed plans and elevations, and a building-regulations set for the build. Doing that survey properly at the start is what avoids the most common and expensive mistake — designing to the wrong 'original' rear wall and only discovering the depth was measured incorrectly once the council or a surveyor checks it.
Should I keep some garden, and how does coverage work?
The 50% coverage rule counts all buildings within the original curtilage — the house, the new extension and any outbuildings or existing garden studio — against half of the original garden area. On a small London plot a deep extension plus a garden office can quietly breach this, tipping the scheme out of permitted development. It is also worth keeping usable outdoor space for daylight, drainage and resale, so the honest design balances internal gain against what the garden is worth to you and to a future buyer.

Which route should I choose for my rear extension?
If your extension fits inside the standard depth limit and there is no Article 4 direction, the permitted-development route with a Lawful Development Certificate is fastest and lowest-risk. If you want the extra depth, the 6m Prior Approval route is the honest answer. If you are extending upward, wrapping around the side, in a conservation area, or own a flat, plan for full planning from day one. We assess which route your property actually qualifies for before any drawings are made, and prepare the building-regulations package the build will need regardless of the planning route. The sequence that works best is to settle the planning route first, because it dictates how much design freedom you have, then to develop the technical drawings that satisfy building control and let the builder price the job accurately. Trying to shortcut the planning question — building a 4m extension on a terrace 'because the neighbour did', for instance — is how homeowners end up with an enforcement notice or an unsellable house years later, when the depth turns out to have needed Prior Approval or full permission that was never obtained.
| Design | Typical route | Neighbour consultation | Depth |
|---|---|---|---|
| Single-storey, within limit | Permitted development + LDC | None | 3m terraced/semi, 4m detached |
| Single-storey, larger | Prior Approval (larger home scheme) | Yes — adjoining neighbours | up to 6m terraced/semi, 8m detached |
| Side return / wraparound | Householder planning | Yes | Design-led |
| Two-storey rear | Householder planning | Yes | Tighter scale and amenity rules |
| Any extension (flat) | Full planning application | Yes | No PD rights |
Related services: House Extension Drawings, Planning Permission, Lawful Development Certificate Drawings.
Frequently asked questions
How far can I extend without planning permission in London?+
Do I need planning permission for a rear extension in a conservation area?+
What is the 45-degree rule for extensions?+
Can I build a rear extension on a flat under permitted development?+
Do I still need building regulations approval if my extension is permitted development?+